BPS Weekly Construction Update – Friday 30 September to Friday 7 October 2022

Dear Neighbour
Please find below a summary of the works taking place across the Battersea Power Station construction site this weekend and into next week.
Whilst some of these works may generate noise, a range of measures are in place to help mitigate the potential impact to our neighbours.
If you have any questions, please do not hesitate to contact us.
Saturday 1 October to Sunday 2 October – 8am to 4pm working hours
- Internal works taking place including snagging and maintenance.
- Internal works by retailers taking place 24/7 completing building works ready for the Power Station opening from 14 October 2022
- External deliveries to the Power Station through Malaysia Square & Power Station Park
- Removal of accommodation units and works in the compound east of the Power Station
- Brand merchandisers access and egress through Switch House West, North Park and Malaysia Square (large volume of people)
Monday 3 to Friday 7 October
- Fit out works to take place inside Switch House East residential reception area
- Installation of rainwater pipes to the external elevations
- Works taking place on the North East chimney
- Works to external Switch House West portal (noisy works, grinding and cutting)
- Night time removals of accommodation units in the compound east of the Power Station between 6pm and 6am
- Facade installation, internal and external works will take place to the buildings to the north of the site.
- Facade installation and internal works will take place to the buildings to the south of the site.
- General logistics and maintenance will be happening to the north and south side of the site and 24 hour security will be on site throughout the weekend.
- External works, facade installation, internal works will take place to the buildings to the north of the site.
- Steel structure, facade installation, internal works will take place to the buildings to the south of the site.
Whilst it is anticipated that these works will generate some noise, measures will be in place to mitigate the potential nuisance to our neighbours.
- Facade works will continue which includes the installation of precast stone and brickwork, aluminium panels and glass reinforced concrete.
- Installation of stickworks and glazing for the NHS centre.
- Continuation of internal fit out works.
- General site logistics including deliveries and the movement of materials.
There are no road closures on Pump House Lane.
Circus Road West
There are no road closures on Circus Road West.
General working hours on-site
In agreement with London Borough of Wandsworth the main site working hours are:
- Monday to Friday: 8am to 8pm
- Saturday: 8am to 5pm
- Sunday and Bank Holidays: works subject to prior approval by the Council.
Agreed out-of-hours works
The London Borough of Wandsworth has agreed that works can take place overnight around the Power Station between the hours of 8pm and 8am, including on Saturday and Sunday. Measures are in place to minimise disturbance to our neighbours and the Construction Managers frequently review planned louder works so that they can be carried out during general site working hours.
If you have any non-urgent questions, please do not hesitate to reply to this email and we will respond to you at the earliest opportunity.
If the matter is urgent, please call the Battersea Power Station construction phone line on 0800 088 4570.
Kind regards
Build Battersea