Nine Elms Park – Community Construction Update
15 September 2022 0

Keltbray will be conducting the below activities this month:
· Continuation of Gasholder excavation and subsequent backfill
· Muckaway of excess soils and contaminated hotspots from basement excavations
· Mechanical treatment of material
· Drainage and utility ducting installation
· Concrete movement and processing activities