Dear NeighbourPlease see below a summary of upcoming works taking place at the R&F One Nine Elms site.Please note that this weekend, Saturday 15 and Sunday 16 October, works will continue to dismantle a tower crane within the One Nine Elms site and this involves the closure of Wandsworth Road in both directions.The road closure is to ensure the required safety exclusion zone for this activity, meaning the road will be closed between the Vauxhall Gyratory and junction with Miles St Junction in both directions for the duration of the works. Pedestrian access will be maintained and traffic management will be in place with sign-posted diversions.Should you have any questions or if you would like to find out more, please do not hesitate to contact us.

Upcoming works at One Nine Elms
Hoarding works along Nine Elms Lane

  • Works are continuing along Nine Elms Lane to dismantle the existing hoarding ahead of landscaping works.
  • Pedestrian diversions are in place throughout these works.

River Tower

  • Continued fit out works, including mechanical and electrical installations.

City Tower

  • Façade installation continues on the exterior of the building.
  • Continued fit out works, including mechanical and electrical installations.

Hotel

  • Continued fit out works, including mechanical and electrical installations.
  • Basement drylining works.

Works planned for Saturday 15 (1pm to 6pm) and Sunday 16 October (10am to 6pm):

  • Saturday 15 October – installation of façade and lifting of materials from deliveries using tower/hoists (1pm to 4pm).
  • Saturday 15 October – works to tower cranes (including crane dismantling works), common tower and hoists (1pm to 6pm).
  • Sunday 16 October – works to tower cranes (including crane dismantling works), common tower and hoists (10am to 6pm).

Out of hours works planned for Monday 17 to Friday 21 October

  • Installation of façade, lifting of materials from deliveries using tower cranes and hoists and concreting pouring  (6pm to 8pm).
  • Delivery and installation of pods (6pm to midnight).
  • The recently completed West Courtyard at Thames City
    Works at Thames City
    Phase 2 (Nine Elms Lane side of the site)Contractors Mace have now completed main works on the N6 building and remaining activity involves the commissioning of building systems and snagging.We will provide further updates on any significant activity.
    Normal Working Hours

    One Nine ElmsSaturday: 8am to 1pmSunday: No worksMonday to Friday: 8am to 6pm

    Thames CitySaturday: 8am to 1pmSunday: No worksMonday to Friday: 8am to 6pm

    Out of Hours Works

    The Environment Enforcement Officer has authorised any out of hours works for the Regulatory Services Partnership Serving the London Boroughs of Merton, Richmond upon Thames and Wandsworth.

    The Council has approved a Section 61 application for extended working hours this coming week on the One Nine Elms site. Extended hours have been approved for the installation of façade, lifting of materials from deliveries using tower cranes, removal of tower cranes, common tower and hoists, concrete pours as well as delivery of pods.These works will take place between: