21 October 2022 0
Dear NeighbourPlease see below a summary of upcoming works taking place at the R&F One Nine Elms site.Thank you for your patience during the recent works to remove a tower crane from the One Nine Elms site and the associated road closures. Should you have any questions or if you would like to find out more, please do not hesitate to contact us.
Upcoming works at One Nine Elms

Hoarding works along Nine Elms Lane

  • Works are continuing along Nine Elms Lane to dismantle the existing hoarding ahead of landscaping works.
  • Pedestrian diversions are in place throughout these works.

River Tower

  • Continued fit out works, including mechanical and electrical installations.

City Tower

  • Façade installation continues on the exterior of the building.
  • Continued fit out works, including mechanical and electrical installations.

Hotel

  • Continued fit out works, including mechanical and electrical installations.
  • Basement drylining works.

Works planned for Saturday 22 (1pm to 6pm) and Sunday 23 October (10am to 6pm):

  • Saturday 22 October – installation of façade and lifting of materials from deliveries using tower/hoists (1pm to 4pm).
  • Saturday 22 October – works to tower cranes, common tower and hoists (1pm to 6pm).
  • Sunday 23 October – works to tower cranes, common tower and hoists (10am to 6pm).

Out of hours works planned for Monday 24 to Friday 28 October

    • Installation of façade, lifting of materials from deliveries using tower cranes and hoists and concreting pouring  (6pm to 8pm).
    • Delivery and installation of pods (6pm to midnight).

Earlier this month our construction partners for One Nine Elms, Multiplex, were delighted to host a family and friends day on site.An annual event at One Nine Elms, this was an opportunity for the Multiplex team to showcase progress to guests of all ages!More details of the event will feature in our next quarterly update.
Works at Thames City
Phase 2 (Nine Elms Lane side of the site)Our construction partners for Thames City, Mace, have  completed the main works on the N6 building and remaining activity involves the commissioning of building systems and snagging.We will provide further updates on any significant activity.
Normal Working Hours

One Nine ElmsSaturday: 8am to 1pmSunday: No worksMonday to Friday: 8am to 6pm

Thames CitySaturday: 8am to 1pmSunday: No worksMonday to Friday: 8am to 6pm

Out of Hours Works
The Environment Enforcement Officer has authorised any out of hours works for the Regulatory Services Partnership Serving the London Boroughs of Merton, Richmond upon Thames and Wandsworth.
The Council has approved a Section 61 application for extended working hours this coming week on the One Nine Elms site. Extended hours have been approved for the installation of façade, lifting of materials from deliveries using tower cranes, common tower and hoists, concrete pours as well as delivery of pods.These works will take place between:
  • Saturday 22 October – 1pm to 6pm
  • Sunday 23 October – 10am to 6pm
  • Monday 24 to Friday 28 October – 6pm to midnight

RFNineElms.png?fit=250%2C94&ssl=1

14 October 2022 0

Dear NeighbourPlease see below a summary of upcoming works taking place at the R&F One Nine Elms site.Please note that this weekend, Saturday 15 and Sunday 16 October, works will continue to dismantle a tower crane within the One Nine Elms site and this involves the closure of Wandsworth Road in both directions.The road closure is to ensure the required safety exclusion zone for this activity, meaning the road will be closed between the Vauxhall Gyratory and junction with Miles St Junction in both directions for the duration of the works. Pedestrian access will be maintained and traffic management will be in place with sign-posted diversions.Should you have any questions or if you would like to find out more, please do not hesitate to contact us.

Upcoming works at One Nine Elms
Hoarding works along Nine Elms Lane

  • Works are continuing along Nine Elms Lane to dismantle the existing hoarding ahead of landscaping works.
  • Pedestrian diversions are in place throughout these works.

River Tower

  • Continued fit out works, including mechanical and electrical installations.

City Tower

  • Façade installation continues on the exterior of the building.
  • Continued fit out works, including mechanical and electrical installations.

Hotel

  • Continued fit out works, including mechanical and electrical installations.
  • Basement drylining works.

Works planned for Saturday 15 (1pm to 6pm) and Sunday 16 October (10am to 6pm):

  • Saturday 15 October – installation of façade and lifting of materials from deliveries using tower/hoists (1pm to 4pm).
  • Saturday 15 October – works to tower cranes (including crane dismantling works), common tower and hoists (1pm to 6pm).
  • Sunday 16 October – works to tower cranes (including crane dismantling works), common tower and hoists (10am to 6pm).

Out of hours works planned for Monday 17 to Friday 21 October

  • Installation of façade, lifting of materials from deliveries using tower cranes and hoists and concreting pouring  (6pm to 8pm).
  • Delivery and installation of pods (6pm to midnight).
  • The recently completed West Courtyard at Thames City
    Works at Thames City
    Phase 2 (Nine Elms Lane side of the site)Contractors Mace have now completed main works on the N6 building and remaining activity involves the commissioning of building systems and snagging.We will provide further updates on any significant activity.
    Normal Working Hours

    One Nine ElmsSaturday: 8am to 1pmSunday: No worksMonday to Friday: 8am to 6pm

    Thames CitySaturday: 8am to 1pmSunday: No worksMonday to Friday: 8am to 6pm

    Out of Hours Works

    The Environment Enforcement Officer has authorised any out of hours works for the Regulatory Services Partnership Serving the London Boroughs of Merton, Richmond upon Thames and Wandsworth.

    The Council has approved a Section 61 application for extended working hours this coming week on the One Nine Elms site. Extended hours have been approved for the installation of façade, lifting of materials from deliveries using tower cranes, removal of tower cranes, common tower and hoists, concrete pours as well as delivery of pods.These works will take place between:
    • Saturday 15 October – 1pm to 6pm
    • Sunday 16 October – 10am to 6pm
    • Monday 17 to Friday 21 October – 6pm to midnight

RFNineElms.png?fit=250%2C94&ssl=1

7 October 2022 0

Dear Neighbour
Please see below a summary of upcoming works taking place at the R&F One Nine Elms site.
Please note that this weekend, Saturday 8 and Sunday 9 October, works will be taking place to dismantle a tower crane within the One Nine Elms site and this will involve the closure of Wandsworth Road in both directions.
This road closure is to create a required safety exclusion zone for this activity, meaning the road will be closed between the Vauxhall Gyratory and junction with Miles St Junction in both directions for the duration of the works. Pedestrian access will be maintained and traffic management will be in place with sign-posted diversions.
Should you have any questions or if you would like to find out more, please do not hesitate to contact us.

Upcoming works at One Nine Elms

Hoarding works along Nine Elms Lane

  • From Monday 9 October works will be taking place to dismantle the existing hoarding along Nine Elms Lane to prepare for landscaping works.
  • Pedestrian diversions will be in place throughout these works.

River Tower

  • Continued fit out works, including mechanical and electrical installations.

City Tower

  • Façade installation continues on the exterior of the building.
  • Continued fit out works, including mechanical and electrical installations.

Hotel

  • Continued fit out works, including mechanical and electrical installations.
  • Basement drylining works.

Works planned for Saturday 8 (1pm to 6pm) and Sunday 9 October (10am to 6pm):

  • Saturday 8 October – installation of façade and lifting of materials from deliveries using tower/hoists (1pm to 4pm).
  • Saturday 8 October – works to tower cranes (including crane dismantling works), common tower and hoists (1pm to 6pm).
  • Sunday 9 October – works to tower cranes (including crane dismantling works), common tower and hoists (10am to 6pm).

Out of hours works planned for Monday 10 to Friday 14 October

  • Installation of façade, lifting of materials from deliveries using tower cranes and hoists and concreting pouring  (6pm to 8pm).
  • Delivery and installation of pods (6pm to midnight).



Progress of works at One Nine Elms

Works at Thames City

Contractors Mace have now completed main works on the N6 building and remaining activity involves the commissioning of building systems and snagging.We will provide further updates on any significant activity.

Normal Working Hours

One Nine ElmsSaturday: 8am to 1pmSunday: No worksMonday to Friday: 8am to 6pm

Thames CitySaturday: 8am to 1pmSunday: No worksMonday to Friday: 8am to 6pm

Out of Hours Works
The Environment Enforcement Officer has authorised any out of hours works for the Regulatory Services Partnership Serving the London Boroughs of Merton, Richmond upon Thames and Wandsworth.
The Council has approved a Section 61 application for extended working hours this coming week on the One Nine Elms site. Extended hours have been approved for the installation of façade, lifting of materials from deliveries using tower cranes, removal of tower cranes, common tower and hoists, concrete pours as well as delivery of pods.These works will take place between:
  • Saturday 8 October – 1pm to 6pm
  • Sunday 9 October – 10am to 6pm
  • Monday 10 to Friday 14 October – 6pm to midnight

RFNineElms.png?fit=250%2C94&ssl=1

30 September 2022 0

Dear Neighbour

Please see below a summary of upcoming works taking place at the R&F One Nine Elms site.

Please note the planned crane dismantling works, which had been scheduled to take place this weekend, will now take place on Saturday 8 and Sunday 9 October owing to the London Marathon taking place on Sunday 2 October.

Road closures will be in place to enable the works to take place, with Wandsworth Road scheduled to be closed in both directions from the Vauxhall Gyratory to Miles Street. Further details will be included in next week’s update.

Should you have any questions or if you would like to find out more, please do not hesitate to contact us.

Upcoming works at One Nine Elms
River Tower

  • Continued fit out works, including mechanical and electrical installations.

City Tower

  • Façade installation continues on the exterior of the building.
  • Continued fit out works, including mechanical and electrical installations.

Hotel

  • Continued fit out works, including mechanical and electrical installations.
  • Basement drylining works.

Works planned for Saturday 1 (1pm to 6pm) and Sunday 2 October (10am to 6pm):

  • Saturday 24 September – installation of façade and lifting of materials from deliveries using tower/hoists (1pm to 4pm).
  • Saturday 24 September – works to tower cranes (including preparation for removal of crane next weekend), common tower and hoists (1pm to 6pm).
  • Sunday 25 September – works to tower cranes (including preparation for removal of crane next weekend), common tower and hoists (10am to 6pm).

Out of hours works planned for Monday 3 to Friday 7 October

  • Installation of façade, lifting of materials from deliveries using tower cranes and hoists and concreting pouring  (6pm to 8pm).
  • Delivery and installation of pods (6pm to midnight).
Works at Thames City
Phase 2 (Nine Elms Lane side of the site)Contractors Mace have now completed main works on the N6 building and remaining activity involves the commissioning of building systems and snagging.

We will provide further updates on any significant activity.

View of progress at One Nine Elms
Normal Working Hours
One Nine Elms
Saturday: 8am to 1pm
Sunday: No works
Monday to Friday: 8am to 6pm
Thames City
Saturday: 8am to 1pm
Sunday: No works
Monday to Friday: 8am to 6pm
Out of Hours Works
The Environment Enforcement Officer has authorised any out of hours works for the Regulatory Services Partnership Serving the London Boroughs of Merton, Richmond upon Thames and Wandsworth.

The Council has approved a Section 61 application for extended working hours this coming week on the One Nine Elms site. Extended hours have been approved for the installation of façade, lifting of materials from deliveries using tower cranes, removal of tower cranes, common tower and hoists, concrete pours as well as delivery of pods.

These works will take place between:

    • Saturday 1 October – 1pm to 6pm
    • Sunday 2 October – 10am to 6pm
    • Monday 3 to Friday 7 October – 6pm to midnight

RFNineElms.png?fit=250%2C94&ssl=1

23 September 2022 0
Dear Neighbour

Please see below a summary of upcoming works taking place at the R&F One Nine Elms site.

As you may be aware, the crane dismantling works and associated road closures which had been planned for last weekend were been postponed following the passing of Her Majesty the Queen.

These works are now confirmed to start on the weekend of Saturday 1 and Sunday 2 October and finish on Saturday 8 and Sunday 9 October. Road closures will be in place to enable the works to take place, with Wandsworth Road scheduled to be closed in both directions from the Vauxhall Gyratory to Miles Street. Further details will be included in next week’s update.

Should you have any questions or if you would like to find out more, please do not hesitate to contact us.

Upcoming works at One Nine Elms

River Tower

  • Continued fit out works, including mechanical and electrical installations.

City Tower

  • Façade installation continues on the exterior of the building.
  • Continued fit out works, including mechanical and electrical installations.

Hotel

  • Continued fit out works, including mechanical and electrical installations.
  • Basement drylining works.

Works planned for Saturday 24 (1pm to 6pm) and Sunday 25 September (10am to 6pm):

  • Saturday 24 September – installation of façade and lifting of materials from deliveries using tower/hoists (1pm to 4pm).
  • Saturday 24 September – works to tower cranes (including preparation for removal of crane next weekend), common tower and hoists (1pm to 6pm).
  • Sunday 25 September – works to tower cranes (including preparation for removal of crane next weekend), common tower and hoists (10am to 6pm).

Out of hours works planned for Monday 26 to Friday 30 September

  • Installation of façade, lifting of materials from deliveries using tower cranes and hoists and concreting pouring  (6pm to 8pm).
  • Delivery and installation of pods (6pm to midnight).
Works at Thames City
Phase 2 (Nine Elms Lane side of the site)

Contractors Mace have now completed main works on the N6 building and remaining activity involves the commissioning of building systems and snagging.

We will provide further updates on any significant activity.

Out of Hours Works
The Environment Enforcement Officer has authorised any out of hours works for the Regulatory Services Partnership Serving the London Boroughs of Merton, Richmond upon Thames and Wandsworth.
The Council has approved a Section 61 application for extended working hours this coming week on the One Nine Elms site. Extended hours have been approved for the installation of façade, lifting of materials from deliveries using tower cranes, removal of tower cranes, common tower and hoists, concrete pours as well as delivery of pods.

These works will take place between:

  • Saturday 24 September – 1pm to 6pm
  • Sunday 25 September – 10am to 6pm
  • Monday 26 to Friday 30 September – 6pm to midnight

  • RFNineElms.png?fit=250%2C94&ssl=1

    16 September 2022 0

    Dear Neighbour

    Please see below a summary of upcoming works taking place at the R&F One Nine Elms site and Phase 2 of Thames City.

    As you may be aware, the crane dismantling works and associated road closures which had been planned for last weekend have been postponed following the passing of Her Majesty the Queen.

    These works are now expected to take place on the weekend of Saturday 24 and Sunday 25 September, and more details will be included in next week’s update.

    Please note, both the One Nine Elms and Thames City sites will be closed on Monday 19 September to allow our colleagues to pay their respects to Her Majesty Queen Elizabeth II. Our thoughts and condolences are with The Royal Family.

    Should you have any questions or if you would like to find out more, please do not hesitate to contact us.

    Upcoming works at One Nine Elms
    River Tower
    • Fit out works continue up to Level 39.
    • Mechanical and electrical installation ongoing up to Level 42.

    City Tower

    • Façade installation continues up to Level 38.
    • Fit out works ongoing on Level 32.
    • Mechanical and electrical installation up to Level 45.

    Hotel

    • Continued fit out works up to Level 14.
    • Mechanical and electrical installation up to Level 12.
    • Basement drylining works will continue.

    Works planned for Saturday 17 (1pm to 6pm) and Sunday 18 September (10am to 6pm):

    • Saturday 17 September – installation of façade and lifting of materials from deliveries using tower/hoists (1pm to 4pm).
    • Saturday 17 September – works to tower cranes (including preparation for removal of crane next weekend), common tower and hoists (1pm to 6pm).
    • Sunday 18 September – works to tower cranes (including preparation for removal of crane next weekend), common tower and hoists (10am to 6pm).

    Out of hours works planned for Tuesday 20 to Friday 23 September

    • Installation of façade, lifting of materials from deliveries using tower cranes and hoists and concreting pouring  (6pm to 8pm).
    • Delivery and installation of pods (6pm to midnight).

Normal Working Hours
One Nine Elms
Saturday: 8am to 1pm
Sunday: No works
Monday to Friday: 8am to 6pm
Thames City
Saturday: 8am to 1pm
Sunday: No works
Monday to Friday: 8am to 6pm
Upcoming works at Thames CityPhase 2 (Nine Elms Lane side of the site)Contractors Mace have now completed main works on the N6 building and remaining activity involves the commissioning of building systems and snagging.

We will provide further updates on any significant activity.

View of Thames City

Normal Working Hours

One Nine Elms
Saturday: 8am to 1pm
Sunday: No works
Monday to Friday: 8am to 6pm

Thames City
Saturday: 8am to 1pm
Sunday: No works
Monday to Friday: 8am to 6pm

Out of Hours Works
The Environment Enforcement Officer has authorised any out of hours works for the Regulatory Services Partnership Serving the London Boroughs of Merton, Richmond upon Thames and Wandsworth.
The Council has approved a Section 61 application for extended working hours this coming week on the One Nine Elms site. Extended hours have been approved for the installation of façade, lifting of materials from deliveries using tower cranes, removal of tower cranes, common tower and hoists, concrete pours as well as delivery of pods.

These works will take place between:

  • Saturday 17 September – 1pm to 6pm
  • Sunday 18 September – 10am to 6pm
  • Tuesday 20 to Friday 23 September – 6pm to midnight

RFNineElms.png?fit=250%2C94&ssl=1

9 September 2022 0

Dear Neighbour

Please see below a summary of upcoming works taking place at the R&F One Nine Elms site and Phase 2 of Thames City.

Please note that the crane dismantling works and associated road closures which had been planned for this weekend, Saturday 10 and Sunday 11 September 2022, have been postponed following the passing of Her Majesty the Queen.  Our thoughts and condolences are with The Royal Family.

Should you have any questions or if you would like to find out more, please do not hesitate to contact us.

Upcoming works at One Nine Elms

River Tower

  • Fit out works continue up to Level 39.
  • Mechanical and electrical installation ongoing up to Level 42.

City Tower

  • Façade installation continues up to Level 38.
  • Fit out works ongoing on Level 32.
  • Mechanical and electrical installation up to Level 45.

Hotel

  • Continued fit out works up to Level 14.
  • Mechanical and electrical installation up to Level 12.
  • Basement drylining works will continue.

Works planned for Saturday 10 (1pm to 6pm) and Sunday 11 September (10am to 6pm):

  • Saturday 10 September – installation of façade and lifting of materials from deliveries using tower/hoists (1pm to 4pm).
  • Saturday 10 September – works to tower cranes (including preparation for removal of crane the following weekend), common tower and hoists (1pm to 6pm).
  • Sunday 11 September – works to tower cranes (including preparation for removal of crane the following weekend), common tower and hoists (10am to 6pm).

Out of hours works planned for Monday 12 to Friday 16 September

    • Installation of façade, lifting of materials from deliveries using tower cranes and hoists and concreting pouring  (6pm to 8pm).
    • Delivery and installation of pods (6pm to midnight).
Upcoming works at Thames City
Phase 2 (Nine Elms Lane side of the site)Contractors Mace have now completed main works on the N6 building and remaining activity involves the commissioning of building systems and snagging.

We will provide further updates on any significant activity.

Normal Working Hours
  • One Nine Elms
      • Saturday: 8am to 1pm
      • Sunday: No works
      Monday to Friday: 8am to 6pm
  •  Thames City
      • Saturday: 8am to 1pm
      • Sunday: No works
      Monday to Friday: 8am to 6pm
Out of Hours Works
The Environment Enforcement Officer has authorised any out of hours works for the Regulatory Services Partnership Serving the London Boroughs of Merton, Richmond upon Thames and Wandsworth.

The Council has approved a Section 61 application for extended working hours this coming week on the One Nine Elms site. Extended hours have been approved for the installation of façade, lifting of materials from deliveries using tower cranes, removal of tower cranes, common tower and hoists, concrete pours as well as delivery of pods.

These works will take place between:

      • Saturday 10 September – 1pm to 6pm
      • Sunday 11 September – 10am to 6pm
      • Monday 12 to Friday 16 September – 6pm to midnight

Contact Us

Email: construction@rfnineelms.co.uk
Call: 08082 819 538
Visit: www.rfnineelms.co.uk 


img_9241.jpg?fit=250%2C151&ssl=1

23 June 2022 0

R&F Properties’ troubled One Nine Elms site in London is due to be completed in November 2023. Last week, Chinese developer R&F agreed a £772m funding package for the site, enabling a full workforce to return to work for the first time since January. 

Read the full story at https://www.constructionnews.co.uk/buildings/troubled-one-nine-elms-site-to-be-completed-by-2023-23-06-2022/